Home / Articles / DEVELOPING: Spotsylvania Board approves Crossroads data center campus in 4-3 vote
Data Centers

DEVELOPING: Spotsylvania Board approves Crossroads data center campus in 4-3 vote

The Spotsylvania County Board of Supervisors approved the 555-acre Crossroads Technology Campus data center project Tuesday night, voting 4-3 to grant the Special Use Permit. Supe...

Alex Wilson
Alex Wilson
NDSM, TownSites | REALTOR® | Local Market & Business Growth Strategist
November 17, 2026
DEVELOPING: Spotsylvania Board approves Crossroads data center campus in 4-3 vote

Fredericksburg · Community Photo

The Spotsylvania County Board of Supervisors approved the 555-acre Crossroads Technology Campus data center project Tuesday night, voting 4-3 to grant the Special Use Permit.

Supervisors Lori Hayes, Drew Mullins, Tim McLaughlin, and Deborah Frazier voted in favor. Supervisors Jacob Lane, David Goosman, and Chris Yakabouski voted against.

How the board voted
4-3 to approve the Special Use Permit
In favor (4)
Lori Hayes
Drew Mullins
Tim McLaughlin
Deborah Frazier
Against (3)
Jacob Lane
David Goosman
Chris Yakabouski
Vote taken Tuesday night, Nov. 17, 2026, at the Board of Supervisors meeting.

What the project is

The campus, known as county case SUP26-0003, would cover about 555 acres in the Lee Hill District — tax parcels 37-A-20 (3215 Eagle Drive), 37-A-21 and 37-A-17D — on the north side of Eagle Drive (Route 736), Lee Hill School Drive (Route 635) and Mills Drive (Route 17), next to the CSX railroad on the west. The land is vacant and forested today.

The general development plan, drawn by Kimley-Horn and dated Aug. 26, 2026, shows seven data center buildings of no more than 75 feet in a two-storey configuration, three electrical substations, utility buildings and water tanks. About 192 acres would be disturbed, inside a development envelope of about 175 acres, with about 366.5 acres — roughly two-thirds of the site — left as open space. The site was filed at about 633 acres in May 2026 and revised to about 555 acres by the time county staff reported on it in September.

Crossroads Technology Campus
The campus, by the numbers
Site~555 acres (filed at ~633 acres)
Buildings7, max 75 ft, two storeys
Floor areaUp to 2,087,000 sq ft
Power894 MW estimated load
Substations3 new 230/34.5 kV, 298 MVA each
Land disturbed~192 acres of 555
Open space~366.5 acres (about two-thirds)
Buffers300-ft vegetated; 400-ft setbacks
Permit conditions30 recommended; no proffers
Figures from the county staff report and general development plan on file (Sept. 16, 2026). The 894 MW load is the applicant’s estimate.

Power is the project's biggest infrastructure question. The applicant's filing with Rappahannock Electric Cooperative, submitted Aug. 7, 2026, estimates an electric load of 894 megawatts, to be served by three new 230/34.5 kV substations of 298 MVA each, with Dominion Energy as the transmission provider. The cooperative notes the load figure is the applicant's unverified estimate. WJLA reported power access is expected in the early 2030s.

The developer says no drinking water would be used to cool the data centers — only reclaimed water — and that backup generators would meet EPA Tier 4 emissions standards with noise-reducing enclosures. The plan includes 300-foot vegetated buffers and 400-foot setbacks between the buildings and nearby homes.

What the developer says it will bring

Kettler, the developer behind RCK Digital Crossroads LLC, describes the campus as an $8 billion investment. Its project site projects more than $37 million a year in county tax revenue once the campus is complete, nearly $1 billion in net fiscal benefit over 25 years, and more than $635 million in personal property tax revenue over that period. It says the campus would support more than 220 permanent jobs, including 226 on-site jobs.

Developer projections
The money, as the developer puts it
Investment$8 billion
Tax revenue$37M+ per year at build-out
Net fiscal benefit~$1 billion over 25 years
Personal property tax$635M over 25 years
Permanent jobs220+ (226 on-site)
Figures are the developer’s projections, not county estimates. Earlier reporting in September put the projected annual tax revenue at more than $30 million a year.

How the project got here

Timeline
How the project got here
Late 2024Kettler buys about 600 acres on Eagle Drive for $26.3 million.
Wed., May 13, 2026The developer’s attorney sends a legal notice to property owners within 3,000 feet; a community meeting is announced.
Thu., June 4, 2026Developer-hosted community meeting at the Lee Hill Community Center.
Tue., Aug. 11, 2026Board votes 4-2 to back a statewide moratorium on data centers.
Wed., Aug. 26, 2026Board votes 3-2 to cap data centers at 45% of industrial land.
Wed., Sept. 16, 2026Planning Commission recommends approval 4-2, and 4-2 that the project conforms to the comprehensive plan.
Mon., Sept. 21, 2026WJLA reports the $8 billion investment and $30M+ annual tax projection.
Thu., Oct. 8, 2026Planning Commission advances the Comprehensive Plan update 5-0.
Tue., Oct. 27, 2026Board unanimously adopts the five-year Comprehensive Plan update and strips the $1.25-per-$100 equipment tax rate from the document.
Tue., Nov. 17, 2026Board holds a public hearing and votes 4-3 to approve the permit.
Weekly Digest
Get the Newsletter

Every Thursday — local news, events, deals, and new listings. Free forever.

The opposition

The citizens group Safeguard Spotsy has opposed the project all year, raising concerns about generator noise, tree clearing, water use, and property values. At the Planning Commission hearing in September, residents cited tree loss, wildlife, the three substations, generator noise, and building height.

One resident told WJLA the 75-foot-tall buildings would still be visible from her home despite the required 300-foot vegetated buffer. Another raised concerns about backup generator noise. In a June report, residents also raised worries about home values, air quality, and children's asthma, and called for a moratorium.

The group pressed the board again in October, urging supervisors to strip data centers as a targeted industry from the updated Comprehensive Plan. The board adopted the plan instead, keeping the 45 percent cap.

How residents are reacting

The reaction online was swift — and it was not acceptance. On the night of the vote, the Spotsylvania Parent Coalition posted urging followers to start a recall effort against board members who approved the project. The frustration has been building for months: residents packed the Holbert Building in July, and Safeguard Spotsy, the citizens group leading the opposition, released an 80-page report challenging the approvals on the morning of the vote.

The complaints are specific. Lee Hill Elementary sits about 1,600 feet from the site, and parents have raised concerns about construction dust, heavy truck traffic, generator noise, and water demands. One resident argued in a detailed post that 200 to 230 backup generators, tested 20 minutes a month, would mean noise on about nine business days a month, and that the county's sound study did not include generator noise. Another resident told WJLA the 75-foot-tall buildings would still be visible from her home despite the required 300-foot vegetated buffer.

The deeper theme in the comments is that residents feel unheard. At a board meeting in July, one resident told supervisors the process felt like a playbook: residents learn about deals last, officials sign nondisclosure agreements, and dissenters are told there is no better option. Commenters on local posts have echoed that, saying public meetings feel like optics because the decision was already made. The group's flyer for the hearing cited more than 200 diesel generators and 1 million gallons of reuse water a day — figures the group, not the county, is asserting.

The other side of the argument is much smaller online. The developer's case — an $8 billion investment and more than $30 million a year in taxes — is repeated in news coverage, and a minority of commenters defend the economic benefits. But in the largest local threads, including WJLA's reports in June and September that drew hundreds of comments, opposition dominates, and the pro-development voices are heavily challenged.

The county's wider data center picture

Crossroads would be the ninth data center campus the board has approved in Spotsylvania. The county's own figures from August 2026 show 15,469,908 square feet of data centers already approved, with 1,104 acres remaining under the proposed 45 percent cap on industrial land.

Amazon Web Services' Cosner Technology Campus in Massaponax — 329 acres and about 1.9 million square feet — is already under construction in the county.

The county's data center rules tightened all year. In August the board voted 3-2 to cap data center use at 45 percent of industrially zoned land — county staff had recommended 55 percent, and Supervisor Chris Yakabouski had proposed 40 percent. The Planning Commission advanced the updated Comprehensive Plan 5-0 on Oct. 8, and the board adopted it unanimously on Oct. 27, stripping a $1.25-per-$100 data center equipment tax rate from the document. The cap is to be reassessed at the next five-year plan update, or sooner if construction starts on 75 percent of entitled projects.

Next door in Stafford, the Board of Supervisors voted 4-2-1 on Oct. 20 to condemn nine parcels for the county's Northern Reuse Water & Return Wastewater Mains project, a reuse-water line for data centers — the first time the county has used eminent domain for the project. In King George County, Amazon Web Services and the county announced a settlement on Sept. 29 ending the long legal fight over the 869-acre former Birchwood Power Facility, with AWS committing $10 million to the county's career and technical education school as part of a planned investment of about $6 billion expected to bring more than 100 jobs.

What happens next

The data center debate moves to Stafford County on Wednesday, when the Stafford County Planning Commission holds a single public hearing at 6 p.m. on the four Kings Highway Corridor data center proposals — Forest Lane, Sisson North, Sisson South, and Simms Farm.

The permit is a land-use approval; site plans and building permits still follow before construction can begin.

This is a developing story. We will update it as more details become available, including any conditions attached to the permit.

Stay connected to what's happening in Fredericksburg

Stories like this one are why we love this community. Join the GoFXBG Facebook page for local news, events, and the good stuff happening around town, and tell us in the comments what you'd like to see next.